Dept. of Trans. PROGRESS Serial No. Contract No. 06-268-07-47 05-0J9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 73% 05-SCR-1-8.4/9.4 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-20-06 PAVEX CONSTRUCTION DIVISION 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 02240 Total Estimate This Estimate 1. Contract Itms Without Mobil. 802,231.50 335,746.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 802,231.50 335,746.00 5. Mobilization 142,000.00 7,100.00 6. Total Work Completed 944,231.50 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -40,111.58 -12,641.78 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 894,119.92 320,204.22 10. Reduction Amt to Escrow 11. Payment to Escrow 40,110.00 12. Net Pymt. this Estimate 320,204.22