Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-319-09-57 05-0J9404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SCR-1-8.4/9.4 Federal Project: NONE Progress payment No. 05 Payment period ending: 10-26-06 PAVEX CONSTRUCTION DIVISION 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 02240 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,269,560.10 -38,005.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,269,560.10 -38,005.00 5. Mobilization 142,000.00 0.00 6. Total Work Completed 1,411,560.10 7. Deductions -40,200.00 -40,200.00 8. a.Contract Retentions -65,378.26 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 65,378.26 65,378.26 9. Total pay to Contractor 1,371,360.10 -12,826.74 10. Reduction Amt to Escrow -65,370.00 -65,370.00 11. Payment to Escrow 65,370.00 12. Net Pymt. this Estimate -78,196.74