Dept. of Trans. PROGRESS Serial No. Contract No. 09-328-12-22 05-0J9704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 20% 05-SLO-1-11.3/16.2 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-20-09 BROUGH CONSTRUCTION INC 634 PRINTZ ROAD ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,684.04 38,839.94 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 46,684.04 38,839.94 5. Mobilization 21,300.00 21,300.00 6. Total Work Completed 67,984.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 67,984.04 60,139.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 60,139.94