Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-237-07-43 05-0K1004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SB-101-54.0/56.0 Federal Project: ACST-Q101(96) PHG-Q101(96) Progress payment No. 11 Payment period ending: 05-26-06 JOHN MADONNA CONSTRUCTION COMPANY INC P O BOX 5310 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,354,185.68 5,296.50 2.a. Extra Work 128,890.34 20,969.59 b. Adjustment Comp. -9,091.78 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,473,984.24 26,266.09 5. Mobilization 22,000.00 0.00 6. Total Work Completed 1,495,984.24 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,485,984.24 26,266.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,266.09