Dept. of Trans. PROGRESS Serial No. Contract No. 13-169-11-32 05-0K2304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 34% 05-SCR-9-8.4/8.6 Federal Project: ACHS-P009(16) STP Progress payment No. 09 Payment period ending: 06-20-13 PAVEX CONSTRUCTION DIVISION 120 GRANITE ROCK WAY SAN JOSE CA 95136 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 930,315.17 132,026.00 2.a. Extra Work 25,781.67 13,250.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 956,096.84 145,276.00 5. Mobilization 22,400.00 0.00 6. Total Work Completed 978,496.84 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 978,496.84 145,276.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,276.00