Dept. of Trans. PROGRESS Serial No. Contract No. 10-025-12-57 05-0K2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 48% 05-SCR-9-23.8/24.7 Federal Project: 05-SCR-9-7.7/ .0 NONE 05-SCR-9-7.8/ .0 Progress payment No. 05 Payment period ending: 01-20-10 JOHN MADONNA CONSTRUCTION COMPANY INC P O BOX 5310 SAN LUIS OBISPO CA 93405 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 531,209.50 7,787.70 2.a. Extra Work 29,770.10 14,862.56 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 560,979.60 22,650.26 5. Mobilization 21,500.00 0.00 6. Total Work Completed 582,479.60 7. Deductions -17,750.00 -5,000.00 8. a.Contract Retentions -28,048.98 -1,132.51 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 536,680.62 16,517.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,517.75