Dept. of Trans. PROGRESS Serial No. Contract No. 09-021-15-09 05-0K9604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 67% 66% 05-SB-101-12.8/24.9 Federal Project: OTS Progress payment No. 05 Payment period ending: 01-20-09 MODERN ALLOYS INC 11172 WESTERN AVENUE STANTON CA 90680 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 772,465.43 196,495.30 2.a. Extra Work 7,284.69 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 779,750.12 196,495.30 5. Mobilization 120,000.00 6,000.00 6. Total Work Completed 899,750.12 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 899,750.12 202,495.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 202,495.30