Dept. of Trans. PROGRESS Serial No. Contract No. 09-082-14-55 05-0L0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 63% 05-MON-198-4.3/4.6 Federal Project: NONE Progress payment No. 05 Payment period ending: 03-20-09 CRUCO CONSTRUCTION GROUP INC 2443 FOUNDRY PARK AVENUE FRESNO CA 93706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 333,837.18 11,933.75 2.a. Extra Work 10,229.31 1,108.21 b. Adjustment Comp. 2,796.09 0.00 3. Materials on Hand 4. Earned Subject to Retention 346,862.58 13,041.96 5. Mobilization 6. Total Work Completed 346,862.58 7. Deductions -2,364.45 -1,193.37 8. a.Contract Retentions -17,343.13 -652.10 b. Unsatisfactory Prog. 0.00 2,865.82 c. Reduction after 95% Comp. 9. Total pay to Contractor 327,155.00 14,062.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 14,062.31