Dept. of Trans. SEMI-FINAL Serial No. Contract No. 05-188-14-13 05-0L0504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SLO-1-37.0/42.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 06-09-05 UNION ASPHALT INC P O BOX 1280 SANTA MARIA CA 93456 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 395,342.09 0.00 2.a. Extra Work 8,216.28 1,146.24 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 403,558.37 1,146.24 5. Mobilization 6. Total Work Completed 403,558.37 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -1,246.88 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 1,246.88 0.00 9. Total pay to Contractor 393,558.37 1,146.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,146.24