Dept. of Trans. PROGRESS Serial No. Contract No. 07-024-11-44 05-0L1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 29% 10% 05-SLO-1-20.4/21.5 Federal Project: 05-SLO-101-7.6/32.1 ACST-P079(34) PE-P079(34) Progress payment No. 02 Payment period ending: 01-20-07 PACIFIC RESTORATION GROUP INC P O BOX 77038 CORONA CA 92877 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 111,075.50 75,162.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 111,075.50 75,162.00 5. Mobilization 47,500.00 22,500.00 6. Total Work Completed 158,575.50 7. Deductions -1,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 157,575.50 96,662.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 96,662.00