Dept. of Trans. PROGRESS Serial No. Contract No. 09-111-15-54 05-0L2304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 24% 05-MON-198-22.9/23.3 Federal Project: NONE Progress payment No. 02 Payment period ending: 04-20-09 M G E UNDERGROUND INC P O BOX 4189 PASO ROBLES CA 93447 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 111,676.05 28,762.86 2.a. Extra Work 346.79 346.79 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 112,022.84 29,109.65 5. Mobilization 9,038.30 1,902.80 6. Total Work Completed 121,061.14 7. Deductions -2,490.96 -2,490.96 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 118,570.18 28,521.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,521.49