Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-067-10-16 05-0L3504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SCR-9-10.9/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 02-29-08 VALENTINE CORPORATION P O BOX 9337 SAN RAFAEL CA 94912 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 897,647.02 61,975.68 2.a. Extra Work 12,812.71 3,300.68 b. Adjustment Comp. 600.02 600.02 3. Materials on Hand 4. Earned Subject to Retention 911,059.75 65,876.38 5. Mobilization 28,755.00 0.00 6. Total Work Completed 939,814.75 7. Deductions -26,197.56 -6,197.56 8. a.Contract Retentions -42,259.17 0.00 b. Unsatisfactory Prog. 0.00 6,175.98 c. Reduction after 95% Comp. 42,259.17 42,259.17 9. Total pay to Contractor 913,617.19 108,113.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,113.97