Dept. of Trans. FINAL Serial No. Contract No. 08-136-14-02 05-0L3504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SCR-9-10.9/ .0 Federal Project: NONE Progress payment No. 08 Payment period ending: 02-29-08 VALENTINE CORPORATION P O BOX 9337 SAN RAFAEL CA 94912 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 900,112.02 0.00 2.a. Extra Work 19,897.72 0.00 b. Adjustment Comp. 41,692.51 0.00 3. Materials on Hand 4. Earned Subject to Retention 961,702.25 0.00 5. Mobilization 28,755.00 0.00 6. Total Work Completed 990,457.25 7. Deductions 8. a.Contract Retentions -42,259.17 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 42,259.17 0.00 9. Total pay to Contractor 990,457.25 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00