Dept. of Trans. PROGRESS Serial No. Contract No. 06-360-08-45 05-0L5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 70% 05-SB-101-38.7/39.6 Federal Project: NONE Progress payment No. 04 Payment period ending: 12-20-06 JOHN MADONNA CONSTRUCTION COMPANY INC P O BOX 5310 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 770,872.20 54,967.20 2.a. Extra Work 2,791.92 2,791.92 b. Adjustment Comp. -8,792.00 -8,792.00 3. Materials on Hand 4. Earned Subject to Retention 764,872.12 48,967.12 5. Mobilization 34,800.00 0.00 6. Total Work Completed 799,672.12 7. Deductions -180,321.25 0.00 8. a.Contract Retentions -38,243.61 -2,448.36 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 581,107.26 46,518.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,518.76