Dept. of Trans. PROGRESS Serial No. Contract No. 07-024-11-44 05-0L5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 83% 05-SB-101-38.7/39.6 Federal Project: NONE Progress payment No. 05 Payment period ending: 01-18-07 JOHN MADONNA CONSTRUCTION COMPANY INC P O BOX 5310 SAN LUIS OBISPO CA 93403 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 782,944.20 12,072.00 2.a. Extra Work 2,791.92 0.00 b. Adjustment Comp. -8,792.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 776,944.12 12,072.00 5. Mobilization 34,800.00 0.00 6. Total Work Completed 811,744.12 7. Deductions -10,000.00 170,321.25 8. a.Contract Retentions -38,847.21 -603.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 762,896.91 181,789.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 181,789.65