Dept. of Trans. PROGRESS Serial No. Contract No. 08-112-08-33 05-0L6204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 8% 05-SLO-5710 Federal Project: NONE Progress payment No. 01 Payment period ending: 04-20-08 WYSONG CONSTRUCTION COMPANY 8720 EL CAMINO REAL NO B ATASCADERO CA 93422 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,057.60 30,057.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 30,057.60 30,057.60 5. Mobilization 6. Total Work Completed 30,057.60 7. Deductions 8. a.Contract Retentions -3,005.76 -3,005.76 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 27,051.84 27,051.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,051.84