Dept. of Trans. PROGRESS Serial No. Contract No. 10-025-16-08 05-0L70U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 9% 0% 05-SCR-17-6.0/12.6 Federal Project: HSST-P017(103) PG-P017(103) Progress payment No. 01 Payment period ending: 01-20-10 K L M CONSTRUCTION INC 15406 MERIDIAN E SUITE 200 PUYALLUP WA 98375 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 215,385.00 215,385.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 159,851.50 159,851.50 4. Earned Subject to Retention 375,236.50 375,236.50 5. Mobilization 267,500.00 267,500.00 6. Total Work Completed 482,885.00 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 632,736.50 632,736.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 632,736.50