Dept. of Trans. PROGRESS Serial No. Contract No. 10-112-10-10 05-0L70U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 15% 05-SCR-17-6.0/12.6 Federal Project: HSST-P017(103) PG-P017(103) Progress payment No. 04 Payment period ending: 04-20-10 K L M CONSTRUCTION INC 15406 MERIDIAN E SUITE 200 PUYALLUP WA 98375 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 748,503.40 118,702.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 641,712.09 -29,179.19 4. Earned Subject to Retention 1,390,215.49 89,522.81 5. Mobilization 508,250.00 0.00 6. Total Work Completed 1,256,753.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,898,465.49 89,522.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 89,522.81