Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 14-321-12-39 05-0L70U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SCR-17-6.0/12.6 Federal Project: HSST-P017(103) PG-P017(103) Progress payment No. 08 Payment period ending: 06-27-14 K L M CONSTRUCTION INC 15406 MERIDIAN E SUITE 200 PUYALLUP WA 98375 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,268,748.90 103,105.50 2.a. Extra Work 45,526.81 0.00 b. Adjustment Comp. -2,000.00 0.00 3. Materials on Hand 0.00 -638,658.27 4. Earned Subject to Retention 1,312,275.71 -535,552.77 5. Mobilization 535,000.00 26,750.00 6. Total Work Completed 1,847,275.71 7. Deductions -15,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,832,275.71 -508,802.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -508,802.77