Dept. of Trans. SEMI-FINAL Serial No. Contract No. 06-187-12-33 05-0L7804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SLO-46-4.5/4.8 Federal Project: NONE Progress payment No. 08 Payment period ending: 03-10-06 ON GRADE CONTRACTING 18149 MAIN STREET STE 10 JAMESTOWN CA 95327 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 389,449.34 0.00 2.a. Extra Work 15,267.50 5,911.38 b. Adjustment Comp. 4,173.77 4,173.77 3. Materials on Hand 4. Earned Subject to Retention 408,890.61 10,085.15 5. Mobilization 6. Total Work Completed 408,890.61 7. Deductions 0.00 1,269.23 8. a.Contract Retentions -19,472.47 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 19,472.47 0.00 9. Total pay to Contractor 408,890.61 11,354.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,354.38