Dept. of Trans. PROGRESS Serial No. Contract No. 05-299-15-01 05-0L8804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 98% 05-SBT-101-0.0/7.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-19-05 PAVEX CONSTRUCTION DIVISION 330 BLOMQUIST ST REDWOOD CITY CA 94063 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 929,060.23 79,560.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 929,060.23 79,560.00 5. Mobilization 119,000.00 0.00 6. Total Work Completed 1,048,060.23 7. Deductions -24,500.00 -24,500.00 8. a.Contract Retentions -46,453.01 -3,978.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 977,107.22 51,082.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,082.00