Dept. of Trans. PROGRESS Serial No. Contract No. 10-054-09-21 05-0M14U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 1% 1% 05-SB-101-26.5/27.1 Federal Project: NHBR-Q101(156) NH-Q101(156) BRLS-6205(19) Progress payment No. 01 Payment period ending: 02-20-10 SHASTA CONSTRUCTORS INC 4150 FIG TREE LANE REDDING CA 96062 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 86,212.80 86,212.80 2.a. Extra Work 9,962.33 9,962.33 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 96,175.13 96,175.13 5. Mobilization 6. Total Work Completed 96,175.13 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 96,175.13 96,175.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 96,175.13