Dept. of Trans. PROGRESS Serial No. Contract No. 12-081-13-17 05-0M14V4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 46% 05-SB-101-26.5/27.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 03-20-12 SPIESS CONSTRUCTION CO INC PO BOX 2849 SANTA MARIA CA 93457 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 132,369.75 86,658.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 132,369.75 86,658.00 5. Mobilization 13,500.00 4,500.00 6. Total Work Completed 145,869.75 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 145,869.75 91,158.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 91,158.00