Dept. of Trans. PROGRESS Serial No. Contract No. 14-202-13-51 05-0M14V4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-SB-101-26.5/27.1 Federal Project: NONE Progress payment No. 22 Payment period ending: 07-20-14 SPIESS CONSTRUCTION CO INC PO BOX 2849 SANTA MARIA CA 93457 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 711,026.50 1,944.00 2.a. Extra Work 21,411.70 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 732,438.20 1,944.00 5. Mobilization 18,000.00 0.00 6. Total Work Completed 750,438.20 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 750,438.20 1,944.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,944.00