Dept. of Trans. PROGRESS Serial No. Contract No. 05-206-08-01 05-0M7304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 21% 05-SB-1-10.1/10.3 Federal Project: ACNH-4101(4) Progress payment No. 01 Payment period ending: 07-20-05 CONDON JOHNSON AND ASSOCIATES INC P O BOX 12368 OAKLAND CA 94604 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 949,098.86 949,098.86 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 14,336.78 14,336.78 4. Earned Subject to Retention 963,435.64 963,435.64 5. Mobilization 237,500.00 237,500.00 6. Total Work Completed 1,186,598.86 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,200,935.64 1,200,935.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,200,935.64