Dept. of Trans. PROGRESS Serial No. Contract No. 08-142-09-04 05-0M8704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 100% 05-SB-192-13.7/ .0 Federal Project: ACST-4111(4) P-4111(4) Progress payment No. 10 Payment period ending: 05-20-08 SPECIALTY CONSTRUCTION INC 645 CLARION CT SAN LUIS OBISPO CA 93401 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 156,940.50 1,521.00 2.a. Extra Work 768,562.50 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 925,503.00 1,521.00 5. Mobilization 142,000.00 0.00 6. Total Work Completed 1,067,503.00 7. Deductions -80,673.15 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 986,829.85 1,521.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,521.00