Dept. of Trans. PROGRESS Serial No. Contract No. 13-200-07-25 05-0M9704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 36% 05-SCR-1-17.4/26.0 Federal Project: STPG-P001(566) Progress payment No. 01 Payment period ending: 07-20-13 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE CA 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 101,087.50 101,087.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 101,087.50 101,087.50 5. Mobilization 88,000.00 88,000.00 6. Total Work Completed 189,087.50 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 189,087.50 189,087.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 189,087.50