Dept. of Trans. SEMI-FINAL Serial No. Contract No. 13-351-11-53 05-0M9704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SCR-1-17.4/26.0 Federal Project: STPG-P001(566) Progress payment No. 07 Payment period ending: 11-19-13 CORAL CONSTRUCTION COMPANY P O BOX 347 WILSONVILLE CA 97070 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,348,292.13 7,964.88 2.a. Extra Work 170,450.53 11,057.99 b. Adjustment Comp. -13,579.70 -13,579.70 3. Materials on Hand 4. Earned Subject to Retention 1,505,162.96 5,443.17 5. Mobilization 176,000.00 0.00 6. Total Work Completed 1,681,162.96 7. Deductions -30,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,651,162.96 5,443.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,443.17