Dept. of Trans. FINAL Serial No. Contract No. 06-060-10-17 05-0N0104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 05-SB-135-11.7/12.2 Federal Project: NONE Progress payment No. 05 Payment period ending: 09-27-05 A J DIANI CONSTRUCTION CO. INC 295 BLOSSER ROAD SANTA MARIA, CA 93458 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 391,530.19 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 391,530.19 0.00 5. Mobilization 6. Total Work Completed 391,530.19 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 391,530.19 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00