Dept. of Trans. PROGRESS Serial No. Contract No. 06-298-13-40 05-0N4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 8% 05-MON-198-21.1/21.5 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-06 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 234,942.00 234,942.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 234,942.00 234,942.00 5. Mobilization 112,500.00 112,500.00 6. Total Work Completed 347,442.00 7. Deductions 8. a.Contract Retentions -23,494.20 -23,494.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 323,947.80 323,947.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 323,947.80