Dept. of Trans. PROGRESS Serial No. Contract No. 06-360-08-45 05-0N4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 36% 05-MON-198-21.1/21.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-06 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 677,948.00 118,025.00 2.a. Extra Work 3,702.10 2,781.63 b. Adjustment Comp. -146.19 0.00 3. Materials on Hand 4. Earned Subject to Retention 681,503.91 120,806.63 5. Mobilization 142,500.00 0.00 6. Total Work Completed 824,003.91 7. Deductions 8. a.Contract Retentions -34,075.20 -5,524.22 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 789,928.71 115,282.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,282.41