Dept. of Trans. PROGRESS Serial No. Contract No. 07-024-11-44 05-0N4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 53% 49% 05-MON-198-21.1/21.5 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-20-07 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 690,710.00 12,762.00 2.a. Extra Work 4,086.44 384.34 b. Adjustment Comp. -146.19 0.00 3. Materials on Hand 4. Earned Subject to Retention 694,650.25 13,146.34 5. Mobilization 142,500.00 0.00 6. Total Work Completed 837,150.25 7. Deductions -98.50 -98.50 8. a.Contract Retentions -34,732.51 -657.31 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 802,319.24 12,390.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,390.53