Dept. of Trans. PROGRESS Serial No. Contract No. 07-054-10-30 05-0N4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 62% 05-MON-198-21.1/21.5 Federal Project: NONE Progress payment No. 05 Payment period ending: 02-20-07 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,062,879.00 372,169.00 2.a. Extra Work 8,130.71 4,044.27 b. Adjustment Comp. -146.19 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,070,863.52 376,213.27 5. Mobilization 150,000.00 7,500.00 6. Total Work Completed 1,220,863.52 7. Deductions -98.50 0.00 8. a.Contract Retentions -53,543.18 -18,810.67 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,167,221.84 364,902.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 364,902.60