Dept. of Trans. PROGRESS Serial No. Contract No. 07-085-07-41 05-0N4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 76% 05-MON-198-21.1/21.5 Federal Project: NONE Progress payment No. 06 Payment period ending: 03-20-07 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,175,934.30 113,055.30 2.a. Extra Work 8,130.71 0.00 b. Adjustment Comp. -623.19 -477.00 3. Materials on Hand 4. Earned Subject to Retention 1,183,441.82 112,578.30 5. Mobilization 150,000.00 0.00 6. Total Work Completed 1,333,441.82 7. Deductions -98.50 0.00 8. a.Contract Retentions -59,172.09 -5,628.91 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,274,171.23 106,949.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 106,949.39