Dept. of Trans. PROGRESS Serial No. Contract No. 07-171-10-39 05-0N4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-MON-198-21.1/21.5 Federal Project: NONE Progress payment No. 09 Payment period ending: 06-20-07 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,423,717.30 1,020.00 2.a. Extra Work 29,102.31 12,158.35 b. Adjustment Comp. -1,147.14 -342.35 3. Materials on Hand 4. Earned Subject to Retention 1,451,672.47 12,836.00 5. Mobilization 150,000.00 0.00 6. Total Work Completed 1,601,672.47 7. Deductions -98.50 0.00 8. a.Contract Retentions -72,583.62 -641.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,528,990.35 12,194.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,194.20