Dept. of Trans. PROGRESS Serial No. Contract No. 07-234-11-22 05-0N4504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 05-MON-198-21.1/21.5 Federal Project: NONE Progress payment No. 11 Payment period ending: 08-20-07 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,425,517.30 780.00 2.a. Extra Work 40,536.29 0.00 b. Adjustment Comp. -1,147.14 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,464,906.45 780.00 5. Mobilization 150,000.00 0.00 6. Total Work Completed 1,614,906.45 7. Deductions -98.50 0.00 8. a.Contract Retentions -73,245.32 -39.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,541,562.63 741.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 741.00