Dept. of Trans. PROGRESS Serial No. Contract No. 08-266-14-54 05-0N5204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 63% 05-MON-1-20.3/ .0 Federal Project: 05-MON-1-23.3/ .0 NONE 05-MON-1-45.2/ .0 Progress payment No. 03 Payment period ending: 09-20-08 WHITAKER CONTRACTORS INC 2752 CONCRETE COURT PASO ROBLES CA 93446 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 134,410.10 67,500.00 2.a. Extra Work 2,455.74 1,940.15 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 136,865.84 69,440.15 5. Mobilization 6. Total Work Completed 136,865.84 7. Deductions 8. a.Contract Retentions -9,899.70 -3,157.13 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 126,966.14 66,283.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 66,283.02