Dept. of Trans. PROGRESS Serial No. Contract No. 11-235-14-36 05-0N6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 24% 05-SB-1 Federal Project: 05-SB-101 NONE 05-SB-192 Progress payment No. 02 Payment period ending: 08-20-11 BROUGH CONSTRUCTION INC 634 PRINTZ ROAD ARROYO GRANDE CA 93420 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 191,463.31 181,563.31 2.a. Extra Work 1,202.29 1,202.29 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 192,665.60 182,765.60 5. Mobilization 35,720.00 35,720.00 6. Total Work Completed 228,385.60 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 228,385.60 218,485.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 218,485.60