Dept. of Trans. PROGRESS Serial No. Contract No. 25-170-09-38 05-0N7054 PROGRESS PAYMENT VOUCHER %complete: %time: 41% 32% Location: Federal Project: 05-SB-101-10.4/11.1 NONE Progress payment No. 010 Payment period ending: 06-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,680,924.27 1,699,703.69 2. a. Extra Work 430,105.28 92,341.10 b. Adustment Comp. 11,243.08 -2,239.42 3. Materials on Hand 31,043.32 31,043.32 4. Earned Subject to Retention 13,153,315.95 1,820,848.69 5. Mobilization 2,874,728.32 0.00 6. Total Work Completed 15,997,000.95 7. Deductions -13,466.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,014,578.27 1,810,848.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,810,848.69