Dept. of Trans. PROGRESS Serial No. Contract No. 25-260-09-22 05-0N7054 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 43% Location: Federal Project: 05-SB-101-10.4/11.1 NONE Progress payment No. 013 Payment period ending: 09-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,589,093.84 315,889.22 2. a. Extra Work 2,229,348.73 1,314,431.43 b. Adustment Comp. 9,137.12 -2,105.96 3. Materials on Hand 4. Earned Subject to Retention 17,827,579.69 1,628,214.69 5. Mobilization 2,874,728.32 0.00 6. Total Work Completed 20,702,308.01 7. Deductions -23,466.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,678,842.01 1,608,214.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,608,214.69