Dept. of Trans. PROGRESS Serial No. Contract No. 22-203-14-16 05-0N72U4 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 32% Location: Federal Project: 05-SB-101-4.4/7.7 NONE Progress payment No. 016 Payment period ending: 07-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 41,240,240.42 3,005,941.95 2. a. Extra Work 330,721.24 48,124.62 b. Adustment Comp. 1,182,240.22 84,384.00 3. Materials on Hand 1,538,250.30 -150,470.83 4. Earned Subject to Retention 44,291,452.18 2,987,979.74 5. Mobilization 14,345,000.00 0.00 6. Total Work Completed 57,098,201.88 7. Deductions -46,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 58,590,452.18 2,977,979.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,977,979.74