Dept. of Trans. PROGRESS Serial No. Contract No. 22-298-10-53 05-0N72U4 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 40% Location: Federal Project: 05-SB-101-4.4/7.7 NONE Progress payment No. 020 Payment period ending: 10-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 55,124,214.51 4,867,712.39 2. a. Extra Work 705,283.60 82,051.77 b. Adustment Comp. 1,408,526.88 116,182.42 3. Materials on Hand 1,766,064.22 -235,914.00 4. Earned Subject to Retention 59,004,089.21 4,830,032.58 5. Mobilization 14,345,000.00 0.00 6. Total Work Completed 71,583,024.99 7. Deductions -31,858.50 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 73,317,230.71 4,820,032.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,820,032.58