Dept. of Trans. PROGRESS Serial No. Contract No. 23-116-16-25 05-0N72U4 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 52% Location: Federal Project: 05-SB-101-4.4/7.7 NONE Progress payment No. 028 Payment period ending: 04-20-23 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,399,533.62 3,706,004.73 2. a. Extra Work 1,533,743.79 0.00 b. Adustment Comp. 1,617,636.23 8,461.53 3. Materials on Hand 1,249,476.22 -571,850.00 4. Earned Subject to Retention 76,800,389.86 3,142,616.26 5. Mobilization 15,100,000.00 755,000.00 6. Total Work Completed 90,650,913.64 7. Deductions -46,858.50 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 91,853,531.36 3,889,616.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,889,616.26