Dept. of Trans. PROGRESS Serial No. Contract No. 25-323-19-16 05-0N72U4 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 05-SB-101-4.4/7.7 ACNH-Q101(395) Progress payment No. 064 Payment period ending: 11-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 135,045,784.13 0.00 2. a. Extra Work 6,794,482.50 126,169.50 b. Adustment Comp. 2,257,490.11 -23,949.22 3. Materials on Hand 4. Earned Subject to Retention 144,097,756.74 102,220.28 5. Mobilization 15,100,000.00 0.00 6. Total Work Completed 159,197,756.74 7. Deductions -35,432.50 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 159,162,324.24 102,220.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 102,220.28