Dept. of Trans. PROGRESS Serial No. Contract No. 25-357-09-09 05-0N72Y4 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 20% Location: Federal Project: 05-SB-101-4.4/7.7 NONE Progress payment No. 010 Payment period ending: 12-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,670,721.88 469,582.15 2. a. Extra Work 39,108.21 717.60 b. Adustment Comp. -30,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,679,830.09 470,299.75 5. Mobilization 459,318.48 22,965.92 6. Total Work Completed 3,139,148.57 7. Deductions -146,400.00 -146,400.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,992,748.57 346,865.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 346,865.67