Dept. of Trans. PROGRESS Serial No. Contract No. 26-054-08-25 05-0N72Y4 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 1% Location: Federal Project: 05-SB-101-4.4/7.7 NONE Progress payment No. 012 Payment period ending: 02-20-26 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077-5085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,540,505.28 490,962.00 2. a. Extra Work 78,229.40 33,388.13 b. Adustment Comp. -28,200.00 1,800.00 3. Materials on Hand 4. Earned Subject to Retention 3,590,534.68 526,150.13 5. Mobilization 459,318.48 0.00 6. Total Work Completed 4,049,853.16 7. Deductions -145,400.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,904,453.16 521,150.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 521,150.13