Dept. of Trans. PROGRESS Serial No. Contract No. 21-298-08-23 05-0N73U4 PROGRESS PAYMENT VOUCHER %complete: %time: 43% 33% Location: Federal Project: 05-SB-101-7.3/9.6 NONE Progress payment No. 012 Payment period ending: 10-20-21 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,762,655.73 5,148,063.35 2. a. Extra Work 714,013.80 22,282.26 b. Adustment Comp. 579,420.45 -5,296.03 3. Materials on Hand 4. Earned Subject to Retention 34,056,089.98 5,165,049.58 5. Mobilization 9,567,638.10 0.00 6. Total Work Completed 43,623,728.08 7. Deductions -47,964.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 43,575,764.08 5,163,049.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,163,049.58