Dept. of Trans. PROGRESS Serial No. Contract No. 22-080-16-49 05-0N73U4 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 46% Location: Federal Project: 05-SB-101-7.3/9.6 NONE Progress payment No. 019 Payment period ending: 03-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 46,098,781.14 4,010,402.95 2. a. Extra Work 1,283,216.91 42,515.71 b. Adustment Comp. 547,895.88 -10,906.64 3. Materials on Hand 4. Earned Subject to Retention 47,929,893.93 4,042,012.02 5. Mobilization 9,567,638.10 0.00 6. Total Work Completed 57,497,532.03 7. Deductions -47,938.40 -14,684.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 57,449,593.63 4,027,327.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,027,327.52