Dept. of Trans. PROGRESS Serial No. Contract No. 22-332-19-18 05-0N73U4 PROGRESS PAYMENT VOUCHER %complete: %time: 79% 69% Location: Federal Project: 05-SB-101-7.3/9.6 NONE Progress payment No. 027 Payment period ending: 11-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 69,002,791.12 1,261,240.12 2. a. Extra Work 2,138,803.03 207,372.14 b. Adustment Comp. 887,415.52 0.00 3. Materials on Hand 4. Earned Subject to Retention 72,029,009.67 1,468,612.26 5. Mobilization 10,071,198.00 0.00 6. Total Work Completed 82,100,207.67 7. Deductions -72,003.40 -10,065.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 82,028,204.27 1,458,547.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,458,547.26