Dept. of Trans. PROGRESS Serial No. Contract No. 22-361-10-07 05-0N73U4 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 72% Location: Federal Project: 05-SB-101-7.3/9.6 NONE Progress payment No. 028 Payment period ending: 12-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,939,557.84 3,936,766.72 2. a. Extra Work 2,262,065.20 123,262.17 b. Adustment Comp. 867,463.44 -19,952.08 3. Materials on Hand 4. Earned Subject to Retention 76,069,086.48 4,040,076.81 5. Mobilization 10,071,198.00 0.00 6. Total Work Completed 86,140,284.48 7. Deductions -76,829.40 -4,826.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 86,063,455.08 4,035,250.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,035,250.81